Submittal of development permit application to Planning Department. Staff will prepare reports based on information submitted. A CEQA (California Environmental Quality Act) Initial Study is prepared about 3-4 months following submission of a complete application, and is completed once certified by the Planning Commission. The Planning Commission holds a public hearing at the end of the development permit process which takes approximately 6-7 months from submission date.